Project-based management: how to manage an industrial project from quotation to after-sales service without losing margin
From quotation to after-sales service: the method for managing a project without losing margin
- By the Synoptic ERP team
- Published

For special machine builders, industrial equipment manufacturers and all the engineering firms that work on a project basis, profitability is not decided when the order is signed. It is built, or destroyed, at every stage of execution. Between the technical quotation and the maintenance contract, dozens of operational decisions can turn a profitable project into a loss-making one. Here is the complete method, in 8 steps, for managing an industrial project from start to finish without ever losing sight of your lead times, your margin or your cash flow.
Project-based management refers to an industrial operating mode in which each order is unique, complex and takes a long time to execute. A special machine, custom-built industrial equipment, an electromechanical assembly configured to the customer's specifications: in all these situations, the product does not exist before the order, the bill of materials changes during the project and several departments must work together over time. Many types of companies are concerned. Engineering firms, industrial equipment manufacturers, special machine builders, providers of custom services: they all share the same challenge.
How do you keep a 360° view of each project, from the first sales contact to the maintenance contract, without losing part of the margin in the gray areas of execution?
In this context, conventional management tools quickly reach their limits. A spreadsheet cannot track bill of materials changes in real time. A generic ERP cannot link the technical quotation to the time actually spent in the workshop. And without visibility on the cost to completion, it becomes impossible to make the right decisions at the right time.
This article details the 8 key steps for managing an industrial project from start to finish, and explains how an ERP specialized in project-based management turns each step into a profitability lever.
Why project-based management requires a dedicated approach
Before looking at the method, you need to understand what makes project-based management fundamentally different from series production.
In series production, you make the same product several times, with a stable bill of materials, a proven routing and well-controlled times. In project-based management, each order is a project in its own right: a specific bill of materials, resources assigned case by case, ad hoc subcontracting, sometimes several hundred components to manage across multiple bill of materials levels.
An industrial project often spans several months, sometimes more than a year. Meanwhile, the engineering department changes the design, critical components may run short and subcontracting delays may push back delivery. Without rigorous management, these unforeseen events take a direct toll on the margin.
Sales, engineering, purchasing, planning, workshop, subcontracting, quality, delivery, installation, after-sales service. A project mobilizes every department in the company. Without a shared tool, everyone works from their own view of the project, and discrepancies quietly pile up.
A well-costed quotation does not guarantee a profitable project. Execution is what makes the difference: control of time spent, purchasing management, handling of changes, adherence to the schedule, tracking of amendments. A project can be invoiced exactly as planned and still end in a loss if actual costs exceed the target budget.
The 8 steps for managing an industrial project
- Step 1
Sales costing and the technical quotation
Everything starts with a credible quotation. For an industrial project, a generic quotation is not enough. You need a technical quotation that breaks down costs by item (materials, labor, subcontracting, expenses), relies on provisional bills of materials and takes into account the specifics of the customer's specifications.
At this stage, CRM functions are essential to nurture the customer relationship upstream, formalize opportunities, track quotation versions and link sales actions to ongoing files.
Key functions at this stage:
- Costing tool based on a structured technical quotation
- Technical and item configurator for common variants
- Management of quotation versions and tracking of costing changes
- Entry of specific billing terms (down payments, milestones)
- Multilingual documents for export customers
The technical quotation then serves as the reference for margin tracking. It defines the sales budget, the first reference for managing the project.
- Step 2
Creating the project and its budget grid
Once the order is signed, the project is officially created in the ERP. This is when the management mechanism is put in place.
The sales quotation is converted into an order. The project manager takes the sales budget grid and refines it to produce the target budget, in other words the profitability target the project must reach. This dual reading (sales budget vs. target budget) is essential. It separates what was sold from what the project must actually consume to remain profitable.
At this stage, the ERP must allow:
- Creation of the project with its contacts and addresses
- Entry of the detailed budget grid by cost type
- Allocation of design time to the project from the upstream phase
- Entry of the billing plan, with down payments, milestones and retention
- Step 3
The engineering department and the CAD interface
For the vast majority of industrial projects, the engineering department plays a central role. It finalizes the design, adjusts the bill of materials and updates revision levels throughout the project.
The challenge is to connect the engineering department and the ERP seamlessly. A SOLIDWORKS, AutoCAD, Inventor or TopSolid bill of materials must be importable directly into the ERP, without re-entry. Drawing changes must flow through to manufacturing orders in progress, with management of revision levels and tracking of component obsolescence. Material requirements planning (MRP) automatically passes these changes on to upcoming procurement.
This native integration between CAD and the ERP is what makes it possible to launch long-lead purchases before the bill of materials is finalized, a major lever for meeting the lead times of an industrial project.
- Step 4
Purchasing and planning
Once the bill of materials is stable, purchasing can begin and production can be planned. For a long-cycle project, this step concentrates a major share of the risk: component shortages, material price drift, subcontracting delays.
A project-based ERP must offer:
- Management of calls for tender and supplier orders
- Shortage analysis through material requirements planning
- Subcontracting management with work-in-progress tracking
- Control of safety stock and reservation of material batches
- Allocation of purchases to the project for real-time budget tracking
Each purchase allocated to the project automatically feeds the actuals, making it possible to continuously compare the target budget with the committed budget.
- Step 5
Production and time tracking
The workshop then takes over. Manufacturing orders are created, planned, released and tracked. Operators record the time they spend, which is automatically allocated to the project.
The key functions are:
- Creation and management of manufacturing orders
- Resource-based planning with constraint management
- Time tracking by operator, machine and operation
- Manufacturing order reviews and multi-order reviews
- Ongoing communication between sales and production
- Management of workshop incidents through workflow
At this stage, the ratio between planned and actual times becomes the first indicator of drift. A workshop that systematically exceeds costing standards must be spotted quickly, so that either the costing of future projects or the workshop organization can be adjusted.
- Step 6
Financial management during the project
This is where project-based management takes on its full strategic dimension. During execution, the project manager must be able to answer three critical questions at any time:
- How much have I already committed on this project (actual and committed)?
- How much do I still need to commit to finish (remaining commitments)?
- What will my final margin be (projected margin)?
To do this, the ERP calculates two essential indicators.
The cost to completion adds up what has already been spent and what remains to be spent to deliver the project. It is updated at each cut-off (monthly or weekly, depending on the company's pace).
The projected margin compares this cost to completion with the expected final revenue. It makes it possible to detect drift several months before delivery, and therefore to act: renegotiate an amendment, optimize a cost item, make a subcontracting decision.
Project cash flow management completes this setup. With billing plans sometimes spread over 12 or 18 months, a project's cash position matters as much as its final margin. Synoptic ERP lets you define configurable billable milestones (down payments on order, on technical delivery, on commissioning) and track actual collections against forecasts.
- Step 7
Delivery, installation and the project review
The project does not end when the equipment leaves the factory. For many manufacturers, it includes on-site delivery, installation, commissioning and even training of the customer's teams.
The ERP must allow:
- Management of delivery addresses and products to be delivered
- Scheduling of installation teams and tracking of their time
- Equipment management (tools, consumables, transport)
- Triggering of final invoicing according to contractual milestones
When the project is closed, the project review consolidates all the costs incurred (materials, labor, subcontracting, expenses) and compares them with the initial target budget. This review feeds directly into lessons learned for future costing. A type of project that is systematically loss-making must be identified, so as to either improve costing or redirect the sales strategy.
- Step 8
After-sales service and the maintenance contract
An industrial project does not end at delivery. It continues over time with after-sales service and maintenance contracts, which often account for a significant share of the project's overall margin over its lifetime.
Synoptic ERP lets you move naturally from the project to after-sales service:
- Automatic generation of the customer's installed base from the products delivered
- Creation and management of maintenance contracts
- Configurable billing schedules (monthly, quarterly, annual)
- Opening of customer tickets and scheduling of interventions
- Creation and invoicing of intervention orders
- Tracking of the complete history, machine by machine
For the end customer, this continuity guarantees responsive service. For the manufacturer, it turns after-sales service into a profit center, with a unified view of the file, from the initial quotation to the latest intervention, sometimes several years after delivery.
It is this logic, from quotation to maintenance contract, that defines project-based management as a complete lifecycle.
The 6 levers of structured project-based management
Beyond the steps, six major levers help structure the management of an industrial project. A project-based ERP provides integrated tools for each of them.
| What it covers | Expected benefit | |
|---|---|---|
| Sell | CRM, opportunities, technical quotation, configurator | Accurate costing, improved conversion rate |
| Make it profitable | Target budget, purchase tracking, margin control by project | Margin protected throughout execution |
| Produce | Manufacturing orders, planning, subcontracting, workshop | Lead times met, resources optimized |
| Manage | Cost to completion, projected margin, cash flow, workflow | Timely decisions, drift anticipated |
| Centralize | EDM, technical documents, drawings, contracts | Shared information, secure audits |
| Support | After-sales service, maintenance contracts, installed base, tickets | Responsive service, recurring margin |
These six levers reinforce one another. A good sales phase improves costing, which structures the target budget, which guides production, which feeds financial management, which is archived in the EDM and which prepares after-sales service. It is this overall consistency that sets an ERP truly suited to project-based management apart from a generic ERP with add-on modules.
The 6 indicators to track so you don't lose margin
To manage an industrial project effectively, six key indicators deserve constant attention.
| Definition | Purpose | |
|---|---|---|
| Target budget | Cost target set by the project manager | Reference for management |
| Actual and committed | Costs already consumed or ordered | Measure of consumption to date |
| Remaining commitments | Costs still to be spent to deliver | Anticipation of drift |
| Cost to completion | Actual, committed and remaining commitments | Final view of the total cost |
| Projected margin | Expected final revenue minus the cost to completion | Forecast profitability |
| Projected cash flow | Upcoming receipts and disbursements | Cash management |
A project-based ERP automatically calculates these six indicators from the data entered in the various modules: quotations, purchases, manufacturing orders, time records, invoices. They are displayed in a consolidated view for each project and feed management dashboards through the integrated business intelligence.
The concrete benefits of a project-based ERP
For manufacturers moving from spreadsheet-based management to a dedicated ERP, the gains can be measured at several levels.
- On margin: early detection of drift makes it possible to act during execution, rather than discovering the loss in the final review. On projects worth several hundred thousand euros, one point of margin gained more than covers the ERP investment.
- On lead times: coordination between sales, engineering, purchasing and production reduces shortages and waiting times. Long-lead purchases can be launched while the bill of materials is being finalized, which shortens time-to-market.
- On cash: controlling cash flow by project avoids collection delays that weigh on working capital requirements. Billing milestones are triggered automatically on the scheduled dates.
- On quality of service: customers get clear visibility on the progress of their project. Lead time confirmations are reliable, everyone involved has access to the same information through the EDM, and after-sales service starts with a complete history of the file.
- On lessons learned: project reviews feed a costing reference base that becomes more accurate project after project. Recurring gaps between planned and actual become opportunities for continuous improvement.
Which manufacturers is project-based management relevant for?
The project-based operating mode concerns all manufacturers that produce unique or barely standardized goods to customer specifications. The most typical profiles are:
- Builders of special machines and custom industrial equipment.
- Industrial equipment manufacturers working for the automotive, aerospace, rail and defense sectors.
- Engineering firms that manage their own design and manufacturing projects.
- Providers of custom services (integrators, turnkey contractors).
- Boilermaking, welded fabrication and sheet metal manufacturers working on large projects.
- Manufacturers of custom street furniture or architectural furniture.
- Producers of equipment for laboratories and healthcare.
If your company sells projects that take more than a few weeks to execute, whose bill of materials changes during manufacturing, and whose profitability depends on your ability to coordinate several departments over time, then your business falls under project-based management.
Synoptic ERP, the ERP for project-based manufacturers for more than 40 years
Synoptic ERP is published by Proges Plus, an independent French company based in Willems, Lille, Lyon and Nantes. For more than 40 years, we have supported manufacturing SMEs in managing their complex projects, with particular attention to special machine builders, equipment manufacturers and engineering firms working to customer specifications.
Synoptic ERP natively covers the entire project cycle, from technical quotation to maintenance contract: CRM, technical quotation, configurator, target budget, CAD interface, planning, time tracking, cost to completion calculation, projected margin, cash flow, project review, EDM, after-sales service. The solution is modular, adapts to your organization, and connects with your existing tools (CAD, MES, workshop barcode scanners, accounting, external EDM).
Project-based management FAQ
What is project-based management in manufacturing?
Project-based management refers to an industrial operating mode in which each customer order is treated as a unique project, with its own bill of materials, its own schedule and its own budget tracking. It contrasts with series production, where the same products are made repeatedly from standardized routings. It typically concerns special machine builders, industrial equipment manufacturers, engineering firms and providers of custom services.
What is the difference between the sales budget and the target budget?
The sales budget is the amount costed at the time of the quotation, which serves as the basis for negotiation with the customer. The target budget is the profitability target set by the project manager once the order has been won. It represents what the project should actually cost the company to achieve the expected margin. The distinction separates the sales view (what was sold) from the operational view (what the project must consume).
How is a project's cost to completion calculated?
The cost to completion is calculated by adding three elements: actual costs (costs already consumed), committed costs (costs ordered but not yet received or allocated) and remaining commitments (costs still to be spent to finish the project). It is updated at each cut-off, monthly or weekly, and makes it possible to anticipate the final margin several months before delivery.
What is the projected margin?
The projected margin is a project's forecast margin, calculated by subtracting the cost to completion from the expected final revenue. It helps identify drift during execution, and therefore act before it is too late: renegotiate an amendment, optimize a cost item, make a subcontracting decision.
Is a spreadsheet enough to manage an industrial project?
For simple, short and infrequent projects, a spreadsheet can do the job. But as soon as projects get longer, bills of materials change and several departments contribute to the same file, the spreadsheet reaches its limits: no automatic updates, no link with purchases and time records, risk of manual errors, loss of history. A project-based ERP centralizes all this data and calculates the indicators in real time.
What are the key indicators to track on a project?
Six indicators are essential: the target budget (cost target), actual and committed (consumption to date), remaining commitments (upcoming costs), cost to completion (final view of the total cost), projected margin (forecast profitability) and projected cash flow (cash management). These six indicators give a project manager a complete view to manage the project at any time.
How do you go from quotation to maintenance contract in a project-based ERP?
A structured project-based ERP covers the entire lifecycle of a project in eight steps: technical quotation, project creation and budget grid, engineering and CAD interface, purchasing and planning, production and time tracking, financial management during the project, delivery and project review, then after-sales service and maintenance contracts. This continuity ensures that no information is lost between steps and that the margin is tracked throughout the cycle, including the maintenance phase.
Is Synoptic ERP suitable for special machine builders?
Yes. Synoptic ERP has been used for more than 40 years by special machine builders, industrial equipment manufacturers, engineering firms and providers of custom services. The solution natively covers technical quotations, the target budget, the CAD interface with the main software on the market (SOLIDWORKS, AutoCAD, Inventor, TopSolid), planning, the calculation of the cost to completion and projected margin, project cash flow, and the management of after-sales service and maintenance contracts.